IPMDAR Schedule Export Options Dialog Box
Use this dialog box to export schedule data to an IPMDAR file.
In order to export schedule data to an IPMDAR file, you must first select IPMDAR Schedule Data in the Publish Data To group on the Deltek Acumen Options dialog box Platforms (IPMDAR) page. After you select this option, and you select a project in the Projects pane on the S1 // Project tab that is not an IPMDAR schedule project, Acumen enables the option on the S1 // Projects tab.
Field | Description |
---|---|
Project | Select the project that you want to export. The list includes all projects in the workbook and defaults to the project you selected in the Projects Pane. |
Contract | If you have previously imported a list of contracts, use the drop-down to select one, or click the ellipses button and use the Manage Contracts dialog box to add or edit a contract. |
Contractor | If you have previously imported a list of contractors, use the drop-down to select one, or click the ellipses button and use the Manage Contractors dialog box to add or edit a contractor. |
Export only calendars in use | (Optional) Select if you want to export only those calendars that are in use. Leave blank if you want to export all calendars in the project. |
Configure Fields | Click to display the Configure Activity Fields dialog box to edit and configure activity fields. You must select a field for Work Package ID or Control Account ID. Selecting a field for Task Planning Level is optional. |
Custom Fields | (Optional) Click to display the Configure Custom Fields dialog box to edit and configure custom fields. |
Export File | Specify the IPMDAR file to which you want to export the data. You can enter a path and file name or click the ellipses to select a folder and file. |
Append Month + Year to file name (MMMYY) | Select this option to append the month and year to the file name. This is useful if you want to use the same file name every time you export because by adding MMMYY, it makes the filename unique. |
OK | When you click OK, the data is exported to the specified file. OK is enabled when all required fields have been completed. |
Cancel | Click to cancel the export. |
- Related Topics:
- Display the IPMDAR Schedule Export Options Dialog Box
Use this dialog box to export schedule data to an IPMDAR file. - IPMDAR Schedule Export Validations
When you export schedule data to an IPMDAR file, Acumen performs certain validations at the control account, work package, and task planning level. - Configure Activity Fields Dialog Box
Use this dialog box to configure the activity fields for exporting schedule data to an IPMDAR file. - Configure Custom Fields Dialog Box
Use this dialog box to configure the custom fields for exporting schedule data to an IPMDAR file.
Parent Topic: IPMDAR Platform Integration